Risk register

Village Hall Roof Replacement Risk Register

The structural replacement of the roof on the local village hall, including associated works and community liaison during the construction period.

riskimpactlikelihoodownermitigation
Hidden structural decay discovered in roof trusses during tear-offHighMediumLead Structural EngineerConduct non-destructive testing and visual inspection of accessible areas prior to full tear-off; include a provisional sum in the budget for emergency timber reinforcement.
Extended period of heavy rain halting external roofing worksMediumHighSite ManagerSchedule critical roofing phases during historically drier months; ensure all exposed areas are tarped and secured at the end of each workday; maintain a buffer of five working days in the program for weather delays.
Unforeseen costs due to price volatility of roofing materialsMediumMediumProject ManagerLock in material prices with the supplier via fixed-price contracts before commencement; secure a 10% contingency fund specifically for material escalation.
Injury to the public or workers from falling debrisHighLowHealth and Safety OfficerInstall full-height hoarding and covered walkways around the perimeter; enforce hard hat zones for all personnel; conduct daily site safety briefings.
Noise and dust complaints from neighboring propertiesMediumMediumCommunity Liaison OfficerDistribute a project timeline to neighbors two weeks prior to start; schedule noisy activities for mid-morning to mid-afternoon; use dust suppression methods during tear-off.
Damage to internal contents or finishes due to water ingress during roof removalHighLowSite ManagerRemove or seal all valuable internal items before work begins; install temporary waterproof membranes immediately after tear-off, regardless of weather forecast.
Loss of access to the hall for scheduled community eventsMediumHighHall Committee ChairIdentify and book alternative venues for all major events occurring during the construction window; communicate closures clearly via signage and social media.