Risk register

Village Hall Roof Replacement Risk Register

Management of risks associated with the structural replacement of the village hall roof, covering construction, financial, and community impact phases.

riskimpactlikelihoodownermitigation
Discovery of rotten timber joists or compromised wall plates during roof strippingHighMediumLead Structural EngineerConduct non-invasive structural survey and core sample testing prior to contractor mobilization to establish a realistic contingency budget and scope.
Sustained heavy rainfall or high winds exceeding safe working thresholdsMediumHighSite ManagerSchedule critical lifting operations and open-roof periods during the historically driest months of the year and secure temporary weatherproofing membranes immediately upon stripping.
Unforeseen structural repairs exceed the allocated contingency fundHighMediumProject TreasurerSecure a fixed-price contract with a defined scope of work and negotiate a pre-agreed rate for additional structural works before ground breaks.
Unsecured site access leads to public injury or vandalismHighLowHealth and Safety OfficerInstall and maintain a 2-meter high hoarding with locked access points and post clear signage prohibiting entry during all working hours.
Construction noise exceeds acceptable levels for adjacent residential propertiesMediumHighCommunity Liaison OfficerPublish a detailed noise schedule to residents one month prior to start and restrict high-decibel activities (e.g., jackhammering) to mid-day weekdays only.
Delivery of roofing materials is delayed due to supplier stock shortagesMediumMediumProcurement OfficerPlace orders for long-lead items (tiles/slates) and primary structural timber at the contract signing stage before site works commence.
Fall of debris from roof height injuring workers or passersbyHighLowSite ManagerErect debris netting and toe boards on all scaffolding levels and designate a protected pedestrian walkway with overhead shielding.
Damage to internal hall contents or finishes due to dust ingressMediumMediumFacilities ManagerSeal all internal doorways and ventilation openings with plastic sheeting and tape before stripping begins and remove internal furniture to storage.