Risk register

Village Hall Roof Replacement Project Risk Register

Management of risks associated with the structural replacement of the roof for the local village hall, covering construction, financial, and community impacts.

riskimpactlikelihoodownermitigation
Hidden structural decay discovered upon removal of existing roofing materialsHighMediumLead Structural EngineerConduct invasive probe inspections on three non-visible structural points prior to full demolition to estimate repair scope and cost.
Severe weather events halt exterior construction workMediumMediumSite ForemanSchedule critical external works during the historically driest months and secure temporary weatherproof membranes immediately after section completion.
Budget overrun due to unforeseen structural repairsHighMediumProject ManagerAllocate a 15% contingency fund specifically for structural remediation and secure a pre-approved credit line for emergency materials.
Supply chain delay for specialized roofing materialsMediumLowProcurement OfficerPlace orders for long-lead items four weeks before the construction start date and identify a secondary local supplier for standard tiles.
Community noise complaints disrupt work schedulesLowHighCommunity Liaison OfficerDistribute a notice to residents detailing work hours and noise expectations two weeks prior and establish a direct phone line for immediate feedback.
Damage to internal hall contents during material transportMediumLowSite Safety OfficerClear and cover all internal furniture and equipment before scaffolding erection and restrict access to the hall during material delivery.
Discovery of hazardous materials such as asbestos in old roof liningHighLowHealth and Safety OfficerCommission a pre-demolition asbestos survey and ensure contractors hold valid asbestos removal licenses if present.