Risk register

Village Hall Roof Replacement Project Risk Register

Management of risks associated with the structural replacement of the main roof covering and supporting timbers at the local village hall

riskimpactlikelihoodownermitigation
Discovery of extensive dry rot or wet rot in roof timbers during stripping of old feltHighMediumLead Structural SurveyorEngage a specialist timber surveyor for a pre-construction intrusive inspection of accessible roof voids to estimate repair scope and cost
Prolonged heavy rainfall preventing safe external roofing worksMediumHighSite ForemanSchedule critical high-level works during historically drier months and maintain temporary waterproof coverings on exposed sections overnight
Cost of unforeseen structural repairs exceeds the allocated contingency fundHighMediumProject ManagerSecure a fixed-price repair agreement with the structural carpentry subcontractor prior to commencement of roof stripping
Contractor withdrawal due to workload pressure causing project standstillHighLowVillage Hall Committee ChairInclude a penalty clause for non-performance in the contract and identify a pre-vetted backup roofing contractor ready to mobilize
Noise and dust from roofing works disrupt scheduled community meetingsMediumHighCommunity Liaison OfficerAgree a strict work schedule with the contractor that excludes peak community usage hours and implement dust suppression measures
Damage to internal plasterwork or contents due to falling debrisMediumMediumSite ForemanInstall protective sheeting and barriers in the hall interior before starting any external stripping or removal work
Failure of new roofing material to meet local planning aesthetic requirementsLowLowPlanning Compliance OfficerObtain written approval for material samples and color finishes from the local planning authority before ordering bulk materials